Taipei

Operation & Maintenance Project of Wugu Water Pump

Organization

Northern Region Engineering Office, Taiwan Area National Freeway Bureau, MOTC

Work Content
  • Design output flow rate: 9.5M3/sec
  • Equipment units: 6 water pumps, 3 sludge dredging machines, 3 generators, 2 sets of conveyor belts, 4 sand pumps, 1 crane, etc.
五府股抽水站

Regular Maintenance of Sewage Treatment Plant

Organization

Vocational Training Center, Department of Labor, Taipei City Government

Work Content
  • Sewage treatment capacity: 200CMD

Regular Inspection and Maintenance of Sewage Treatment Plant Equipment

Organization

National Research Institute of Chinese Medicine

Work Content
  • Design treatment capacity: Domestic sewage: 500CMD, laboratory wastewater: 200CMD
  • Equipment units: Trash rack, crude wastewater collection well, mixing tank, primary sedimentation tank, blending tank, biological aeration tank, final sedimentation basin, rapid filter basin, sludge thickening basin, sludge dewatering equipment, discharge well, etc.

Maintenance of Xiang-An Building Electrical System

Organization

Air Navigation & Weather Services, CAA, MOTC

Work Content
  • Main transformers: 11.4KV/440V 500KW×2, 11.4KV/208V/120V 500KW×2
  • Generator capacity: 500KW×3
  • Uninterrupted electrical supply system: 360KVA×1